Trump Calls the Texas Data Center Pause a Mistake, Saying the Industry Could Be Bigger Than Oil

In an interview released Friday, the president said Texas was wrong to hold up data center approvals. Gov. Greg Abbott's office said fewer than 10 percent of operators had supplied the power and water data the state asked for.

Wade Ramos

August 8, 20262 min read

Texas data center infrastructure - illustration, Jake Team LLC
Texas data center infrastructure - illustration, Jake Team LLC

President Donald Trump said Texas is making a mistake by pausing data center approvals, in an interview with Punchbowl News released Friday.

"I saw Texas the other day sort of is against data centers. I think it's a mistake," Trump said.

He compared the industry's potential to the one Texas is best known for. "For Texas to say no to data centers is a mistake in the sense that it could be bigger than oil," he said.

Trump also said data centers are "tremendously important for the economics," and that "when a community wants it, it means a lot of money is going to come into that community." He said that if he were a governor he would want the projects and would cut taxes to attract them, and that other countries would benefit if the United States slowed development.

What Texas actually did

Gov. Greg Abbott announced the pause on Monday, Aug. 3, in a letter to the Public Utility Commission of Texas and the Electric Reliability Council of Texas.

It halts approvals for new data centers seeking to connect to the ERCOT grid until state agencies audit them. The audits are to assess tax breaks, power and water consumption, cooling methods, efforts to mitigate community impact and facility ownership. Projects that do not clear the review are to be denied grid connection.

The order does not ban data centers, and it does not cover projects that supply their own power on site rather than connecting to the grid.

The state's response

Abbott spokesperson Andrew Mahaleris said the pause followed a shortfall in information from the industry, saying fewer than 10 percent of data centers had provided the power and water usage figures the state requested.

He cited a 500 percent increase in peak electricity demand tracked by ERCOT.

"Simply put, Texans must come first," Mahaleris said.

The numbers behind the dispute

ERCOT is tracking more than 1,800 projects in its interconnection queue, representing over 474 gigawatts of requested capacity, which is more than five times the grid's record peak demand. Abbott has said about 90 percent of new connection requests come from data centers.

Separate reporting on the state's earlier voluntary survey put the response rate differently, at fewer than a third of 341 data centers. The two figures describe different measures, and the state has not published a reconciliation.

Projections cited in that reporting put data center water use in Texas at between 29 billion and 161 billion gallons a year by 2030.

Neither the governor's office nor the White House has announced any change to the Texas order.

Sources

https://www.texastribune.org/2026/08/07/donald-trump-texas-data-centers-greg-abbott/

https://www.texastribune.org/2026/08/03/texas-data-center-project-audit-greg-abbott/

https://www.kut.org/energy-environment/2026-08-05/texas-data-centers-water-power-energy-use-environment

Share

Wade Ramos

Wade Ramos writes about community life, schools, public safety, and local events in Dallas.

Related Stories

More in Sport